BRIEF-Voltalia gives update on Brazilian SMG and Vamcruz sites

June 8 (Reuters) - Voltalia SA :

* Brazilian construction work update: all turbines completed at Sao Miguel do Gostoso site; first revenues expected in Q3 2015

* Wind parks will not be started right away because of a delay in the installation of the grid connection

* Commissioning Vamcruz site expected to be significantly ahead of schedule

Source text: bit.ly/1cGEI4w Further company coverage: (Gdynia Newsroom)