BRIEF-Wartsila wins 240 mln eur power plant order in El Salvador

viernes 16 de octubre de 2015 03:09 GYT

Oct 16 (Reuters) - Wartsila Oyj Abp :

* Says will supply 378 MW Flexicycle power plant to Energia del Pacifico S.A. in Acajutla, El Salvador.

* Says the value of order is approximately 240 million euros.

* Says the order is estimated to be included in its order book in 2016, and plant completion is scheduled for 2018.

* Says the plant will be the first in Central America to be fired by LNG-based natural gas. Source text for Eikon: Further company coverage: (Reporting By Helsinki Newsroom)