Odebrecht misses deadline to transfer Colombia project, fines to begin

viernes 10 de junio de 2016 18:26 GYT
 

By Julia Symmes Cobb

BOGOTA, June 10 (Reuters) - Construction firm Odebrecht has not yet found a company to take over a large portion of its $849.7 million majority stake in a project to make Colombia's Magdalena River more navigable and will now begin paying fines for failing to start construction, the government said on Friday.

Odebrecht, Latin America's largest engineering conglomerate, said in May it would relinquish 50 to 75 percent of its participation in the Navelena consortium, tasked with deepening the river to allow the passage of large shipping barges.

The project contract allows Brazil-based Odebrecht to pass the majority of its 87 percent stake in Navelena to another firm in extraordinary circumstances. Odebrecht had until Saturday, when construction was set to begin, to find a substitute.

Without an alternative company in place, Odebrecht will be required to pay fines of 20.86 million pesos per day, the equivalent of 30 minimum monthly salaries, Cormagdalena, the government agency overseeing the project said in a statement.

Odebrecht told Reuters it had no immediate comment on the matter.

Twelve multinational firms, their names kept confidential, had expressed interested in the stake, Cormagdalena said in a statement.

Should a substitute not be found within 30 days, Cormagdalena could begin the process of terminating the contract, the agency said.

The Navelena consortium, which also includes Colombian firm Valorcon, is set to fund most of the project and profit from toll charges for seven years after its upgrade of the waterway.   Continuación...