BRIEF-Enbridge - Griffith, Ind. terminal pipelines restart seen Thursday

jueves 27 de febrero de 2014 15:12 GYT
 

Feb 27 (Reuters) - Enbridge Inc -

* Enbridge says all pipelines expected to be returned to service later today

* Enbridge says 975 barrels of crude oil released from station piping inside Griffith terminal in Griffith, Ind.

* Enbridge says repairs were completed last night and work is underway to safely restart all pipelines in and out of the Griffith terminal

* Enbridge says majority of free product was recovered, collection of remaining oil progressing well though cold weather in the Chicago area is affecting effort